Harbor & Pine website rebuild is forecast to lose money
Harbor & Pine Hotels · Grace Kim · ends Oct 30, 2026 · forecast margin −10%
Priya Shah is over capacity and holding up Harbor & Pine website rebuild and Copperline driver app redesign
Copperline Logistics · Grace Kim · ends Nov 20, 2026 · forecast margin 54%
Meridian patient portal UX: "Accessibility remediation" is late
Meridian Health Partners · Ben Carter · ends Dec 18, 2026 · forecast margin 45%
Delivery is at risk; financial is fine.
Lumen Analytics · Hannah Brooks · ends Oct 23, 2026 · forecast margin 54%
Studio website refresh: "Studio site launch" has slipped 35 days
Marketing · Dana Whitfield · ends Nov 20, 2026
Verdant product launch campaign: "Client creative & claims approval" waiting on the client for 38 days; 1 more milestone affected
Verdant Foods · Ben Carter · ends Nov 6, 2026 · forecast margin 51%
Delivery and finances are on track.
Brightwater Credit Union · Ben Carter · ends Oct 30, 2026 · forecast margin 48%
Delivery and finances are on track.
Operations · Ryan Walsh · ends Nov 27, 2026
Delivery and finances are on track.
Northwind Cycles · Hannah Brooks · ends Nov 13, 2026 · forecast margin 44%
Delivery and finances are on track.
Orchard Education · Grace Kim · ends Dec 11, 2026 · forecast margin 61%
| Project | Status | Main issue | Schedule | Hours used | Forecast margin | Forecast vs budget |
|---|---|---|---|---|---|---|
| Harbor & Pine website rebuild Harbor & Pine Hotels · Grace Kim · Fixed fee · ends Oct 30, 2026 (was Aug 28, 2026) | At risk | Harbor & Pine website rebuild is forecast to lose money +1 more | Blocked | 1,448 h / 1,050 h · forecast 1,788 h | −10% target 45% | — |
| Copperline driver app redesign Copperline Logistics · Grace Kim · Fixed fee · ends Nov 20, 2026 | At risk | Priya Shah is over capacity and holding up Harbor & Pine website rebuild and Copperline driver app redesign | Blocked |
| 54% target 45% |
| — |
| Meridian patient portal UX Meridian Health Partners · Ben Carter · Time & materials · ends Dec 18, 2026 | At risk | Meridian patient portal UX: "Accessibility remediation" is late | Late | 707 h / 1,300 h | 45% target 45% | — |
| Lumen dashboard design sprint Lumen Analytics · Hannah Brooks · Time & materials · ends Oct 23, 2026 | At risk | Delivery is at risk; financial is fine. | Blocked | 51 h / 240 h | 54% target 45% | — |
| Studio website refresh Marketing · Dana Whitfield · Internal · ends Nov 20, 2026 (was Oct 16, 2026) | Watch | Studio website refresh: "Studio site launch" has slipped 35 days | Moved | 87 h / 220 h | — | −$7.6k |
| Verdant product launch campaign Verdant Foods · Ben Carter · Fixed fee · ends Nov 6, 2026 (was Sep 15, 2026) | Watch | Verdant product launch campaign: "Client creative & claims approval" waiting on the client for 38 days; 1 more milestone affected | Waiting on approval | 343 h / 560 h | 51% target 45% | — |
| Brightwater member onboarding redesign Brightwater Credit Union · Ben Carter · Time & materials · ends Oct 30, 2026 | On track | None open | On track | 461 h / 900 h | 48% target 45% | — |
| Delivery operations toolkit Operations · Ryan Walsh · Internal · ends Nov 27, 2026 | On track | None open | On track | 161 h / 330 h | — | −$3.2k |
| Northwind discovery & brand strategy Northwind Cycles · Hannah Brooks · Time & materials · ends Nov 13, 2026 | On track | None open | On track | 67 h / 300 h | 44% target 45% | — |
| Orchard course platform UX Orchard Education · Grace Kim · Fixed fee · ends Dec 11, 2026 | On track | None open | On track | 499 h / 1,000 h | 61% target 45% | — |